Back to projects

PROJECTS > INFRASTRUCTURES

Tramway Network Alicante. Line 9. Benidorm-Benidorm Intermodal

Tramway Network Alicante. Line 9. Benidorm-Benidorm Intermodal
Next Previous

The works carried out are divided into three major actions

  • The new Benidorm Intermodal Line 9 Tram stop, (which has meant the closure of the Disco-Benidorm stop), has parallel platforms, each 76.5 metres long, and the Tram stops' own equipment, including signalling, lighting and passenger information installations (intercom, public address system and ticketing).
  • 6,000 square metres of landscaped area between the bus station and the new stop, connected by 125 metres of pedestrian paths. It connects the existing bike lane to the north, so that has allowed these two facilities to link with the "Palacio de los Deportes de Benidorm".
  • Electrification of the 1.4-kilometre-long section linking this new stop with Benidorm station and the start of the future electrification of line 9 (Benidorm-Denia), which in its first phase should reach Altea. The ATP ZSI 127 signalling system has also been implemented.

 

Budget:
3.200.000 Euros

Finishing works:
July 2018